 
				Case Study
Crosby, TX - Two Story Post-Hurricane Home Elevation
Situation
In  the  aftermath  of  Hurricane  Harvey,  a  devastating  natural  disaster  that 
                                   unleashed  a  record-breaking  60.58  inches  of  rainfall  in  2017,  the  suburban 
                                   Houston   community   faced   a   daunting   challenge.   This   property   suffered extensive  flood  damage,  and  rebuilding  was  awarded  through  the  Harris 
                                   County  (TX)  Hurricane  Recovery  Program.  This  community,  like  others  in  the 
                                   region,  had  to  retool  its  flood  zones  and  building  codes  in  the  wake  of  this 
                                   devastation.    Traditionally,    the   go-to   approach      would    involve   shallow 
                                   foundations   supported   by   piers   or   columns   to   elevate   structures   above 
                                   floodwaters. This approach, however, creates the likelihood of future structural 
                                   damage  from  soil  expansive  heave  and  shrinkage. A  challenge  arose  to  find  a 
                                   sustainable  and  competitively  priced  long-term  foundation  system  that  could 
                                   not  only  withstand  future  floods  but  also  meet  the  evolving  standards  and 
                                   regulations set forth by the county. 
Scope of Work
The primary objective of this project was to devise a robust foundation design 
                                        capable of elevating a two-story structure above the  newly established  flood 
                                        elevation   levels   mandated   in   the   aftermath   of   Hurricane   Harvey.   This 
                                        elevation  was  imperative  not  only  to  safeguard  the  property  against  future                           flood  damage  but  also  to  counteract  the  threat  of  soil  expansion,  which  can 
                                        cause an uplift to the structure. Cost-effectiveness was a top consideration as 
                                        well.  Helical  piles  are  a  proven  solution,  striking  a  balance  between  resiliency 
                                        and  affordability.  Cobalt  Engineering  designed  the  2078  square-foot  home 
                                        above  the  new  flood  elevation.  Many  battered  piles  were  incorporated  into 
                                        the design, due to the additional lateral loading on the structure. 
Anchor System
86 total. 64 vertical and 22 battered piles installed. 2-7/8" OD pipe piles with single 12" and single 14" helix were used. Single helix opted over multi-helix due to the presence of expansive clay soils, preventing the need to advance the piles deeper to ensure all helices are past the active soil. The foundation design required a minimum of 5 Kips for compression load and 2.5 Kips for tension load on the battered piles. While these loads may appear light in nature for a two-story structure, the spacing was kept to a minimum to allow for additional piles to increase the overall lateral capacity.
Result
Cantsink helical piles proved to be an exceptional choice for this project. The entire pile installation process was completed within three days, allowing the framer to proceed with no downtime. The piles reached a minimum embedment of 13', surpassing the 10' active zone requirement. Additionally, the minimum torque achieved for each pile exceeded 2,000 foot-pounds, which translates to an ultimate load more than three times what is required. The project was completed within the proposed budget, demonstrating that Cantsink helical piles not only deliver superior performance but also offer a cost-effective elevation support solution for both one- and two-story structures.


