Case Study

Cumming, GA, Temporary Shoring For Construction Site

Situation

During construction of a detention pond near a Cumming, GA, Park-and-Ride lot, Cantsink was engaged to install a temporary shoring wall that would protect the road to the parking lot.

Scope of Work

The job was accomplished in three stages, each stage requiring two - three days' work. In all, 81 helical anchors were installed for the shored area measuring roughly 140 linear feet.

This temporary shoring allowed for construction of an 18" tall retaining wall as close as 10 feet from the roadway above, while preventing sinking or damage to the roadway during the construction. No utilities were encountered during the installation, which allowed work to be completed without interruption.

The foundation wall crew was permitted to begin construction of the wall footing immediately following completion of the lower-tier shoring. Cantsink anchors were part of the earth retention system, along with the fabric, heavy gauge wire, and reinforcing bars.

Anchor System

81 anchors with 8" helices were used, installed 20 degrees from horizontal. 12" X 12" x ½" tension plates were used to lock the reinforcing members against the slope to restrict lateral movement.

Design Load

15 kips with Eskridge 5,500 # head

Soil Type

Clay

Results

Road stabilized without delay so construction could proceed on schedule. The temporary shoring permitted a safe work environment for the foundation crew to complete the wall structure.

Download PDF

Cantsink
Locations

a city skyline at sunset

Georgia

Georgia

Monday - Friday
8am - 5pm EST

a palm tree on a beach

Florida

Florida

Monday-Friday
8am-5pm EST

a city with tall buildings

Texas

Texas

Monday-Friday
8am-5pm CST